Building Permit Timeline in Ontario
How long does it take to get a building permit? Here's what to expect across GTA municipalities.
Decks under 40 sq m, sheds, fences, interior non-structural alterations
Larger decks, basement finishing, kitchen/bath renovations with plumbing
Additions, secondary suites, structural changes, new construction
The Clock Starts When Your Application is Complete
Processing time begins when the building department receives a complete application. If documents are missing or incorrect, your application may be returned, and the clock resets when you resubmit. This is why 21% of Toronto applications are returned at intake.
Processing Times by City
| City | Simple | Standard | Complex |
|---|---|---|---|
| Toronto | 10-15 business days | 15-25 business days | 30-60+ business days |
| Mississauga | 10-12 business days | 15-20 business days | 25-45+ business days |
| Brampton | 10-15 business days | 15-25 business days | 30-50+ business days |
| Vaughan | 10-12 business days | 15-20 business days | 25-45+ business days |
| Markham | 10-15 business days | 15-22 business days | 25-40+ business days |
| Oakville | 10-12 business days | 15-20 business days | 25-40+ business days |
* Times are in business days and represent typical processing for complete applications. Actual times vary based on application quality, season, and department workload.
The Permit Approval Process
Intake Review
1-3 daysStaff verify your application is complete with all required documents. If incomplete, it's returned here.
Zoning Review
3-7 daysPlanners verify your project complies with zoning bylaws (setbacks, lot coverage, height, use).
Plan Examination
5-15+ daysBuilding officials review drawings for Ontario Building Code compliance (structural, fire safety, etc.).
Revisions (if needed)
VariableIf changes are required, you'll receive a revision letter. Time depends on complexity of changes.
Permit Issuance
1-3 daysOnce approved, you'll receive notification to pay fees and pick up your permit.
What Causes Delays?
Incomplete Application
Adds 2-4+ weeksMissing documents or forms means your application goes back to the queue after you resubmit.
Revision Requests
Adds 1-3 weeks per cycleIf reviewers need changes to drawings, each revision cycle adds time.
Zoning Issues
Adds 2-6+ monthsIf you need a variance, minor variance, or rezoning, expect significant delays.
Peak Season (Spring/Summer)
Adds 1-2 weeksMarch-August is the busiest time for residential permits.
Heritage Designation
Adds 2-4+ weeksHeritage properties require additional review by Heritage staff.
Committee of Adjustment
Adds 2-4 monthsIf variances are required, you'll need to go through Committee of Adjustment first.
How to Get Your Permit Faster
This is the #1 way to avoid delays. Use our pre-check tool to verify completeness.
Online applications are often processed faster than paper submissions.
Check setbacks, lot coverage, and height limits. Zoning issues cause major delays.
Good designers know what building officials look for and submit cleaner drawings.
September-February typically has shorter wait times than spring/summer.
Some municipalities offer meetings to review your plans before formal submission.
When you receive revision requests, turn them around ASAP to stay in the queue.
Detailed Timeline by City
Toronto
Building deptSimple Projects
10-15 business days
Standard Projects
15-25 business days
Complex Projects
30-60+ business days
Note: Toronto Building has service level targets; complex projects take longer. Holidays can extend timelines.
Mississauga
Building deptSimple Projects
10-12 business days
Standard Projects
15-20 business days
Complex Projects
25-45+ business days
Note: Online applications may be faster. Peak seasons (spring/summer) can add delays.
Brampton
Building deptSimple Projects
10-15 business days
Standard Projects
15-25 business days
Complex Projects
30-50+ business days
Note: Pre-submission consultations can help expedite complex applications.
Vaughan
Building deptSimple Projects
10-12 business days
Standard Projects
15-20 business days
Complex Projects
25-45+ business days
Note: Service level agreements apply. Incomplete applications restart the clock.
Markham
Building deptSimple Projects
10-15 business days
Standard Projects
15-22 business days
Complex Projects
25-40+ business days
Note: Online portal shows real-time status. Pre-approved plans available for some projects.
Oakville
Building deptSimple Projects
10-12 business days
Standard Projects
15-20 business days
Complex Projects
25-40+ business days
Note: Express service available for simple permits meeting all requirements.
Related Resources
Don't Waste Time on Rejections
A rejected application can add weeks to your timeline. Our pre-check catches common issues before you submit.
Run Free Pre-CheckProcessing times are estimates based on municipal service level targets and typical experiences as of December 2025. Actual times vary. Always check with your local building department for current wait times.